TriMark Executive Outlines Equipment Rollout Playbook for Menu Launches

Bryan Musgrove of TriMark USA says location readiness, manufacturer lead times and delivery packaging should be planned before new menu equipment reaches stores.

Aleksandra NovakNovember 1, 20265 min read7 views

A stainless steel toaster, holding cabinet, serving utensils and consolidated shipping cartons are arranged in a bright commercial kitchen, with shelving and open workflow space in the background.

Equipment rollouts for new menu items require planning that begins well before the food reaches the plate, according to Bryan Musgrove, divisional senior director on national accounts for TriMark USA. Musgrove, who has worked on numerous rollouts tied to menu additions, outlined practices aimed at making deployments across locations more seamless.

Create a location-by-location playbook

Musgrove recommends creating a rollout playbook that accounts for differences among locations. TriMark worked with a brand that needed new toasters to add toasted sandwiches to an existing breakfast lineup of biscuits and wraps. In some locations, electrical capacity was already maxed out, he said. In others, a small mall or urban site lacked counter space for a toaster, requiring the brand to create space by adding shelving or another table, which affected workflow.

The playbook should distinguish locations that can support plug-and-play installation from those that need additional support, Musgrove said. That assessment helps teams anticipate electrical, space and workflow issues before equipment arrives.

Build the schedule around manufacturer lead time

Scheduling should be driven by the manufacturer's lead time, not only by the desired launch date. Musgrove gave the example of a manufacturer that might be able to produce 200 units but at a rate of 10 per week, which would take 20 weeks. In another scenario, a manufacturer might have inventory for the first 50 units, then need to order parts from overseas, adding eight weeks before completing the rest.

For a menu item launching with a marketing campaign tied to a specific season or occasion, Musgrove advises working backward from the desired launch date to establish an achievable timeline. The schedule should reflect production and parts availability rather than assume uniform delivery.

Consolidate packaging to simplify deliveries

Packaging can also be reworked to make deliveries easier. Instead of shipping smaller wares directly to locations in their original boxes, operators can consider asking their dealer to consolidate and repackage items into one package per location. TriMark worked with a brand adding macaroni and cheese to its lineup of sides. The addition required visual holding cabinets, pans and serving scoops in varying sizes. TriMark combined the items into one package per location, including instructional materials and exterior labeling so managers knew exactly what they were receiving.

Plan for a smoother launch

Following these practices—from determining which locations need more support to simplifying deliveries—can help ensure a smoother rollout, according to Musgrove. If all goes as planned, the new menu item will generate buzz and increase traffic. The guidance focuses on readiness, scheduling and logistics, with examples showing how electrical capacity, counter space, production timing and packaging can affect an equipment rollout.